Evaluation of claims
Contents |
[edit] Introduction
Claims commonly arise between the parties to construction contracts. This can be as a result of delays, changes, unforeseen circumstances, insufficient information and conflict. Claims might be made for things such as loss and expense, extension of time and liquidated damages. The contract should set out exactly what can constitute a claim and how it should be dealt with. There may also be claims associated with the appointment of consultants.
Evaluation is the process of assessing disputed issues associated with a claim. The article, Evaluation and Preparation of Claims in Construction Projects, suggests the evaluation process most commonly relates to lost money or extensions of time - or “...costs associated with prolongation and costs associated with disruption. As Burden of Proof is on the claimant, the claimant must show that there is a direct link (causal link) between the breach (cause) and the loss (effect) thereby sustained.”
[edit] Examining the evaluation process
According to the book, Evaluating Contract Claims by John Mullen, Peter Davison, the claim evaluation process can include an examination of duty, cause, effect and damage. The book states, “The prime source of information for any evaluation has to be the contract between the parties and its requirements. There is no substitute for reading the contract and any incorporated relevant documents. Regrettably, this is often a starting point more often honoured in the breach than in observance in practice.”
Claims must be properly constituted and documented. This means:
- Proper legal entitlement must be established.
- Cause and effect must be clearly demonstrated by contemporaneous records.
- Additional costs must be backed up by full supporting documents.
Records from both parties may be considered in the evaluation of claims. Records may include:
- Tender and contract documentation.
- Staffing/labour records.
- Materials/equipment records.
- Correspondence.
- Photographs/videos.
Any other documents exchanged between the parties related to scheduling, pricing, risk or eventual project outcome may also be used in the evaluation of claim. These records should be accurate and include substantial details, “...to the standard required in formal dispute resolution procedures under English law,” according to Mullen and Davison.
Certain types of contract may be more susceptible to claim issues than others.
The fixed price contract, which is defined by The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB) as, ‘…a contract where the price is agreed and fixed before construction starts’. Under a fixed price agreement, contractors may be compelled to pursue evaluation of claims based on changes resulting in disputes over money and time. The establishment of a contract baseline, including a defined scope, schedule and conditions of work, can set conditions that can help to formalise the consequences of changes made by the client that may justify additional compensation for the contractor.
[edit] Related articles on Designing Buildings
- Alternative dispute resolution for construction ADR.
- Arbitration in the construction industry.
- Contract claims in construction.
- Contract claims procedure.
- Dispute avoidance.
- Evaluation.
- Fixed price construction contract.
- Lump sum contract.
- Mediation in construction.
[edit] External resources
- LawTeacher.net, Evaluation and Preparation of Claims in Construction Projects.
- John Mullen and Peter Davison, Evaluating Contract Claims.
- Society of Construction Law.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February